Representative
Systems
(click on small picture to get larger image
and more information) |
| Soil Nailing/Shotcrete
|
 |
 |
 |
 |
| SR 210 - Rte 30,
San
Bernardino |
Sand Hill Road, Palo Alto |
Sculptured Wall Sand Hill
Road,
Palo Alto |
Rancho Bernardo, San Diego |
| Temporary and Permanent
Tiebacks |
 |
 |
 |
 |
Evergreen Reservoir,
San Jose |
Tamien to Lick, San Jose |
Tamien to Lick, San Jose |
Flamingo Road, Las Vegas |
| Rock Anchors
|
|
Dam Strengthening |
|
 |
  |
 |
|
| SUNDIAL Bridge, Redding |
Eastside Reservoir,
Hemet |
Combie Dam, Grass Valley |
|
| Design-Build Shoring |
 |
 |
 |
New Bloomingdale's
Department
Store,
San Francisco |
Conservatory of Music,
San Francisco |
Varian Physics Building
Expansion, Stanford University |
| Tiedowns |
|
 |
 |
| Rte 70 at Pulga |
SR 125 Toll Road San Diego |
| Micropiles |
|
|
|
 |
 |
 |
 |
| Oroville-Quincy Highway |
Palo Alto Medical Associated |
New Bloomingdale's Department Store,
San Francisco |
San Francisco Airport |
| Soil Nailing/Shotcrete |
|
 |
SR 210
- Rte 30, Segment 1, 2 and 3A, San Bernardino, CA
140,000 sq. ft. of permanent soil nail/shotcrete
retaining wall.
Owner: San Bernardino Associated Governments
(SANBAG)
Prime Contractor: Yeager Skanska Inc.
|
|
back |
| |
|
 |
Sand Hill Road Widening, Palo Alto, CA
Stanford University and the City of Menlo Park jointly contracted to improve
the intersection at Sand Hill Road and Alpine Road. Part of the reconstruction
required installation of a permanent soil nail retaining wall to support
the embankment at the residence of the Stanford University Provost.
Owner: Stanford University
Prime Contractor: Top Grade Construction, Inc. |
| back |
| |
|
 |
The permanent soil nail wall is completed with a sculptured shotcrete
layer to provide an esthetically pleasing appearance that blends in
with the natural surroundings.
|
| back |
| |
|
 |
Rancho Bernardo, San Diego, CA
45,000 sq. ft. of permanent soil nails and 20,000 sq. ft. of permanent tieback/shotcrete retaining wall
Owner: Caltrans
Prime Contractor: FCI Constructors Inc. |
| back |
| |
|
| Temporary and Permanent
Tiebacks |
|
 |
Evergreen Reservoir, San Jose,
CA
15,000 sq. ft. of temporary tieback/shotcrete wall
Owner: City of San Jose, CA
Prime
Contractor: Granite Construction Company |
| back |
| |
|
 |
Tamien to Lick, San Jose
CA 35,000 sq. ft. of permanent tieback/shotcrete wall
Shotcrete for permanent facing
Owner: Valley Transportation Authority (VTA)
Prime Contractor: R&L Brosamer, Inc.
|
| back |
| |
|
 |
Placing of reinforcing steel and geocomposite drains
|
| back |
| |
|
 |
Flamingo Road, Las Vegas, NV
Repair of MSE Wall
Severe corrosion of the MSE wall’s reinforcing elements required strengthening of the wall to prevent potential failure. Some 204 Double Corrosion Protected (DCP) prestressed tiebacks were installed through the face of the wall to replace the horizontal loads once carried by the earth reinforcements.
Owner: Nevada Department of Transportation
Prime Contractor: Capriati Construction Corporation
|
| back |
| |
|
| Rock Anchors |
|
 |
SUNDIAL Bridge, Redding, CA
Rock anchors to tie down the 217 ft. high pylon of the stay cable bridge
designed by world renown Spanish designer Santiago Calatrava
Owner: City of Redding
Prime
Contractor: Kiewit Pacific Co. |
|
| back |
| |
|
 |
Eastside Reservoir, Hemet,
CA
High capacity rock anchors to anchor Inlet/Outlet Tower
Owner: Metropolitan Water District of Southern California
Prime
Contractor: Atkinson-Washington-Zachry, A Joint Venture |
| back |
| |
|
| Dam Strengthening |
|
 |
Combie Dam, Grass Valley,
CA
Like many dams built at the beginning of the century, the Combie Dam
was rapidly approaching the end of its design life. Stabilizing the
spillway with prestressed rock anchors was an economical solution to
extend the life of such dams for several years.
Owner: Nevada County Irrigation Department
Prime Contractor: AVAR Construction Systems, Inc. |
| back
|
| |
|
| Design-Build Shoring |
|
 |
New Bloomingdale's Department
Store,
San Francisco, CA
25,000 SF of temporary shoring using soldier beam/lagging with temporary
tiebacks. Scope of work also included underpinning and installation
of 300 kips micropiles inside adjacent building
Owner/Prime Contractor: Westfield Corporation
Driven Pile |
| back |
| |
|
 |
Conservatory of Music, San
Francisco, CA
AVAR provided the temporary shoring and underpinning support for demolition and reconstruction
of this historic building, including the preservation of existing
facades. Work included hand-dug underpinning pits to support existing columns as the basement was lowered by 12 ft.
A new addition adjacent to the existing structure required
30 ft. deep excavation on the property line. AVAR designed and installed
a temporary soldier beam and tieback shoring system for support of the excavation.
Owner: San Francisco Conservatory of Music
Prime Contractor: Swinerton
Builders |
| |
back |
 |
Varian Physics Building Expansion, Palo Alto, CA
Stanford University's expansion of its physics laboratory required excavation of 40 feet below existing site grades adjacent to
an active research facility. Because of the sensitivity
of the magnetic fields generated inside the existing facility, tieback anchors could not be installed
within 20 feet of the source.
AVAR designed a sophisticated
waler system, anchored on either side of the laboratory keeping the
tiebacks away from the critical zones. An incremental stressing sequence
was developed to transfer the loads from the center to the
exterior beams. The balance of the site utilized a soldier beam and tieback system with
shotcrete lagging.
Owner: Stanford University
Prime Contractor: Vance Brown, Inc. |
| |
back |
| Tiedowns |
|
 |
Rte 70 at Pulga, CA
Seismic retrofitting of bridge piers with 150 ft. long, large capacity
Double Corrosion Protection (DCP) tiedowns
Owner: Caltrans
Prime
Contractor: ACC West Coast, Inc. |
| back |
| |
|
 |
SR 125 Toll Road San Diego, CA
Permanent Tiedowns for uplift resistance of column
footings for new bridge construction
Owner: Caltrans
Prime
Contractor: Otay River Constructors |
| back |
| |
|
| Micropiles |
|
 |
Oroville-Quincy Highway, CA
New retaining walls and temporary shoring for construction of the
highway embankment widening. Scope of work included the installation
of 80 each 12" diameter micropiles and the design and construction
of 20,000 SF of a soil nail/shotcrete wall for temporary shoring.
Owner: FHWA Federal Highway Administration
Prime
Contractor: Viking/Stimpel-Wieblhaus, JV
|
| back |
| |
|
 |
Palo Alto Medical Associated,
Palo Alto, CA
Garage expansion required the addition of new shear walls. One of
these walls extended to the existing basement. Because of the potential
for liquefaction in the upper soils, a deep foundation system was
required. With limited headroom of only eight feet, AVAR proposed
the use of 12-125 kips micropiles.
Owner: Palo Alto Medical Foundation
Prime Contractor: Vance Brown, Inc. |
| back |
| |
|
 |
New Bloomingdale's Department Store,
San Francisco, CA
Owner/Prime Contractor: Westfield Corporation
Micropile drilled with 12 ft. headroom |
| back |
| |
|
 |
San Francisco Airport
Tiedown anchors for uplift resistance of tower bracing
Beam set up to testing apparatus for 500 kip performance test
Owner: City and County of San Francisco
Prime Contractor: FCI Constructors |
| back |
|