AVAR Construction Systems, Inc.
Drilling and Shoring Post-Tensioning Contact us Home
Representative Systems
Current projects 2009/2010

   

Representative Systems
(click on small picture to get larger image and more information)
Soil Nailing/Shotcrete
SR 210 - Rte 30, San Bernardino Sand Hill Road, Palo Alto Sculptured Wall Sand Hill Road,
 Palo Alto
Rancho Bernardo, San Diego

Temporary and Permanent Tiebacks
Evergreen Reservoir,
San Jose
Tamien to Lick, San Jose Tamien to Lick, San Jose Flamingo Road, Las Vegas

Rock Anchors   Dam Strengthening  
 
SUNDIAL Bridge, Redding Eastside Reservoir, Hemet Combie Dam, Grass Valley  

Design-Build Shoring
New Bloomingdale's Department
Store, San Francisco
Conservatory of Music,
San Francisco
Varian Physics Building
Expansion, Stanford University

Tiedowns  
Rte 70 at Pulga SR 125 Toll Road San Diego

Micropiles      
Oroville-Quincy Highway Palo Alto Medical Associated New Bloomingdale's Department Store, San Francisco San Francisco Airport



Soil Nailing/Shotcrete  
SR 210 - Rte 30, Segment 1, 2 and 3A, San Bernardino, CA

140,000 sq. ft. of permanent soil nail/shotcrete
retaining wall.

Owner: San Bernardino Associated Governments (SANBAG)
Prime Contractor: Yeager Skanska Inc.







ˆback
   
Sand Hill Road Widening, Palo Alto, CA

Stanford University and the City of Menlo Park jointly contracted to improve the intersection at Sand Hill Road and Alpine Road. Part of the reconstruction required installation of a permanent soil nail retaining wall to support the embankment at the residence of the Stanford University Provost.

Owner: Stanford University
Prime Contractor: Top Grade Construction, Inc.
ˆback
   



The permanent soil nail wall is completed with a sculptured shotcrete layer to provide an esthetically pleasing appearance that blends in with the natural surroundings.

ˆback
   
Rancho Bernardo, San Diego, CA

45,000 sq. ft. of permanent soil nails and 20,000 sq. ft. of permanent tieback/shotcrete retaining wall

Owner: Caltrans
Prime Contractor: FCI Constructors Inc.
ˆback
   
Temporary and Permanent Tiebacks  
Evergreen Reservoir, San Jose, CA

15,000 sq. ft. of temporary tieback/shotcrete wall

Owner: City of San Jose, CA
Prime Contractor: Granite Construction Company
ˆback
   
Tamien to Lick, San Jose

CA 35,000 sq. ft. of permanent tieback/shotcrete wall

Shotcrete for permanent facing

Owner: Valley Transportation Authority (VTA)
Prime Contractor: R&L Brosamer, Inc.



ˆback
   


Placing of reinforcing steel and geocomposite drains







ˆback
   
Flamingo Road, Las Vegas, NV

Repair of MSE Wall

Severe corrosion of the MSE wall’s reinforcing elements required strengthening of the wall to prevent potential failure. Some 204 Double Corrosion Protected (DCP) prestressed tiebacks were installed through the face of the wall to replace the horizontal loads once carried by the earth reinforcements.

Owner: Nevada Department of Transportation
Prime Contractor: Capriati Construction Corporation
ˆback
   
Rock Anchors  
SUNDIAL Bridge, Redding, CA

Rock anchors to tie down the 217 ft. high pylon of the stay cable bridge designed by world renown Spanish designer Santiago Calatrava

Owner: City of Redding
Prime Contractor: Kiewit Pacific Co.
 
ˆback
   
  Eastside Reservoir, Hemet, CA

High capacity rock anchors to anchor Inlet/Outlet Tower

Owner: Metropolitan Water District of Southern California
Prime Contractor: Atkinson-Washington-Zachry, A Joint Venture
ˆback
   
Dam Strengthening  
Combie Dam, Grass Valley, CA

Like many dams built at the beginning of the century, the Combie Dam was rapidly approaching the end of its design life. Stabilizing the spillway with prestressed rock anchors was an economical solution to extend the life of such dams for several years.

Owner: Nevada County Irrigation Department
Prime Contractor: AVAR Construction Systems, Inc.
ˆback
   
Design-Build Shoring  
New Bloomingdale's Department Store,
San Francisco, CA


25,000 SF of temporary shoring using soldier beam/lagging with temporary tiebacks. Scope of work also included underpinning and installation of 300 kips micropiles inside adjacent building

Owner/Prime Contractor: Westfield Corporation




Driven Pile
ˆback
   
Conservatory of Music, San Francisco, CA

AVAR provided the temporary shoring and underpinning support for demolition and reconstruction of this historic building, including the preservation of existing facades. Work included hand-dug underpinning pits to support existing columns as the basement was lowered by 12 ft.

A new addition adjacent to the existing structure required 30 ft. deep excavation on the property line. AVAR designed and installed a temporary soldier beam and tieback shoring system for support of the excavation.

Owner: San Francisco Conservatory of Music
Prime Contractor: Swinerton Builders
  ˆback
Varian Physics Building Expansion, Palo Alto, CA

Stanford University's expansion of its physics laboratory required excavation of 40 feet below existing site grades adjacent to an active research facility. Because of the sensitivity of the magnetic fields generated inside the existing facility, tieback anchors could not be installed within 20 feet of the source.

AVAR designed a sophisticated waler system, anchored on either side of the laboratory keeping the tiebacks away from the critical zones. An incremental stressing sequence was developed to transfer the loads from the center to the exterior beams. The balance of the site utilized a soldier beam and tieback system with shotcrete lagging.
Owner: Stanford University
Prime Contractor: Vance Brown, Inc.
  ˆback
Tiedowns  
Rte 70 at Pulga, CA

Seismic retrofitting of bridge piers with 150 ft. long, large capacity Double Corrosion Protection (DCP) tiedowns

Owner: Caltrans
Prime Contractor: ACC West Coast, Inc.
ˆback
   

SR 125 Toll Road San Diego, CA



Permanent Tiedowns for uplift resistance of column
footings for new bridge construction

Owner: Caltrans
Prime Contractor: Otay River Constructors
ˆback
   
Micropiles  
Oroville-Quincy Highway, CA

New retaining walls and temporary shoring for construction of the highway embankment widening. Scope of work included the installation of 80 each 12" diameter micropiles and the design and construction of 20,000 SF of a soil nail/shotcrete wall for temporary shoring.

Owner: FHWA Federal Highway Administration
Prime Contractor: Viking/Stimpel-Wieblhaus, JV

ˆback
   
Palo Alto Medical Associated, Palo Alto, CA

Garage expansion required the addition of new shear walls. One of these walls extended to the existing basement. Because of the potential for liquefaction in the upper soils, a deep foundation system was required. With limited headroom of only eight feet, AVAR proposed the use of 12-125 kips micropiles.

Owner: Palo Alto Medical Foundation
Prime Contractor: Vance Brown, Inc.
ˆback
   
New Bloomingdale's Department Store,
San Francisco, CA




Owner/Prime Contractor: Westfield Corporation



Micropile drilled with 12 ft. headroom
ˆback
   
San Francisco Airport

Tiedown anchors for uplift resistance of tower bracing

Beam set up to testing apparatus for 500 kip performance test

Owner: City and County of San Francisco
Prime Contractor: FCI Constructors
ˆback